No AMI, No Problem

A device-level EV tariff program VPPSA runs across 11 municipal utilities with no advanced metering, delivered at 2.5% the cost of the alternative.


What we built
A device-level EV tariff platform: enrollment portal, device integration, dynamic pricing, and billing reconciliation, running across 11 municipal utilities without new utility-side hardware.
Timeline
Discovery through a built platform, delivered against Vermont's mid-2024 Act 55 mandate. Live in production since October 2025 across all 11 member utilities.
Who did the work
Lead PM: Matt Gizmunt. The people who built it are the people on your calls.

How much time do you have? Show:

Switch to the longer version to see more info.

What we built
A device-level EV tariff platform.
Timeline
Live since 2025
Who did the work
Lead PM: Matt Gizmunt

Overview: The short of it

Vermont's Act 55 required every electric utility to offer EV rates by mid-2024. VPPSA had 11 small municipal utilities to serve and no advanced metering to build on. Meter reads happen on foot. Customer data sat in fragmented systems. The mandate called for a working tariff, not a plan.

We built a device-level EV tariff platform that works without utility-side hardware. Customers enroll, connect their EV or charger, and the platform reads usage straight from the device through Enode. A pricing engine sets day-ahead rates from ISO-NE and nudges charging toward off-peak hours. A billing module turns that usage into monthly credits, formatted to drop into whatever billing system each utility already runs.

We delivered it at about 2.5% the cost of a projected AMI rollout, across 11 utilities, with no backend integrations required. The Vermont Public Utilities Commission saw a live demo and backed it. The part we're proudest of: the platform runs across 11 different operational setups without adding overhead to teams that were already stretched thin.

Stats we're proud of

the cost of a projected full AMI deployment
2.5%the cost of a projected full AMI deployment
municipal utilities served on one platform, no backend integrations required
11municipal utilities served on one platform, no backend integrations required
new pieces of utility-side hardware
0new pieces of utility-side hardware
The public Hourly Pricing Program page, where EV owners see the savings on offer and check whether they qualify.

Would this work at our size?

Small team? No AMI? That is the environment we built this in. The same prices-to-devices platform flexes up as a utility adds devices and programs over time.

VPPSA · Joint action agency, 11 municipal utilities, no AMI

11 utilities

Full program: enrollment portal, Enode device integration, ISO-NE pricing engine, off-peak notifications, and billing reconciliation that fits each member's existing system.

Your utility · Adding devices and programs over time

Prices to devices

Same platform, extended as you grow: batteries and inverters through the same device layer, new rates through the same pricing engine, no new hardware in the field.

No AMI? No budget for one? You can still run a modern EV program.